Studio 1 – Pemasangan Baja

Setelah umur kepala sloof 14 hari, pengerjaan struktur baja dimulai. Struktur ini dipilih karena waktu pengerjaannya yang relatif singkat.

image

Lima hari sesudahnya seluruh struktur kolom dan atap terpasang.

image

Timeline H-15 menjelang Lebaran dan H-60 menjelang dipakainya acara Live